Managing a Work Package, Team Manager or Project Manager
Description
Managing a work package is a set of processes to ensure that a work package is accepted, managed, and delivered according to the requirements of the project.
Quality Reviewsare performed to ensure that the work is complete.
When work products are complete, a configuration management system is updated with the latest work products.
Audit Criteria
- Resources are identified and available to complete the plan within work package tolerance
- Check point reports are produced according to work package requirements
- Quality Reviews are held and completed successfully according to work package requirements
Document Templates
Forms
Process Details
References
A Guide to the Project Management Body of Knowledge
- 4.2 Project Plan Execution
- 8.2 Quality Control
Additional Details